Updates: Training Pool

Friday, October 26, 2018

Updated 12:30 p.m., Wednesday, November 7

The training pool's heating system requires a full boiler replacement. That will be an approximately four-week process for the boiler build, shipping and final installation.

The lap pool heating system remains fully operational. Both pools will remain open at this time, but the temperature of the training pool will be lower than usual until its heating system is fully operational.

Due to the changing temperatures, group swim lessons will be relocated to the lap pool and there will not be lap swim lanes in that pool from 9 - 11:30 a.m. on Saturdays. There will be limited lap swim capacity in the training pool. Our online and mobile app schedules should reflect these modifications.

We will continue to post updates in the event of additional activity shifting between the pools and as we know more about the repair timelines for the heating system.

The Downtown Durham YMCA Pool Facebook group will also post updates.